Aalsmeer is a village which consists of almost a third of water and has an equal number of bridges. We took care of the structural design of 9 bridges, including the environmental permit.
Drawing work in Revit
All calculations, both steel and (prefab) concrete, are carried out entirely according to the new Eurocodes. The drawing is completely set up in Revit. Working with a 3D model has had many advantages, especially for making the reinforcement drawings.
Implementation drawings
In addition, all implementation drawings were also made pile plans, form and reinforcement joints for the concrete foundations and the form drawings of the prefabricated bridges, overviews of the steel construction of the bridges and the railing work.